| 1. |
0n Allotment 25 % of the total cost |
| |
|
| 2. |
During Foundation 20 % of the total cost |
| |
|
| 3. |
RCC Structure 20 % of the total cost |
| |
|
| 4. |
Masonry / S. B. Work 15 % of the total cost |
| |
|
| 5. |
Plastering & Flooring 15 % of the total cost |
| |
|
| 6. |
Handing Over 5 % of the total cost |
| |
|